Resource Allocation

FP-2026-035 · Batu Kawan — Week 35 · generated 2026-08-23 09:14 · work covered up to handover to shipping.

Orders required vs completed

2,830 / 2,830

all orders cleared

Boxes handled

232,060

20,942 outer cartons sealed

Total cost to fulfil

RM 84,452

Labour RM 23,376 · Tools RM 1,053 · IDM RM 60,023

Cost per order

RM 29.84

RM 0.36 per box handled

Staff used

15 / 36

peak day · minimised by the solver

Labour-hours incl. overtime

768.3 h

0 h overtime at +50%

Work-ahead achieved

2,062 orders

pre-picked / pre-packed for later days

On-time vs ship-by

100%

avg cleared by 15:37 · GA converged gen ~480

Hard constraints

All constraint checks pass — 12-hour shift cap, breaks, weekly hours, certifications, tool caps, stock & IDM sufficiency and ship-by dates all hold.

Staff Gantt — tasks across the 12-hour shift
ReceivingPut-awayPickingPackingHandoverBreak
Staff member
08:0010:0012:0014:0016:0018:0020:00

Ahmad Abdullah

Crew A · Picking

Li Na Chin

Crew C · Picking

Noraini Koh

Crew B · Picking

Wei Jun Lim

Crew C · Packing

Lakshmi Govindan

Crew A · Packing

Sock Yee Salleh

Crew C · Packing

Ming Xuan Rahman

Crew C · Packing

Kok Keong Sulaiman

Crew C · Packing

Mariam Khor

Crew B · Put-away

Intan Chan

Crew B · Forklift / Reach Truck

Zainab Teoh

Crew B · Picking

Time to clear the day's orders
DayOrders dueCompletedWork-aheadStaffOT hoursCleared by
Mon 2026-08-24450450+1441518:45
Tue 2026-08-25350350+3881518:45
Wed 2026-08-26500500+4821518:45
Thu 2026-08-27400400+5941518:45
Fri 2026-08-28450450+4541218:16
Sat 2026-08-29300300008:00
Sun 2026-08-30380380008:00
Tool load
ToolUnitsTool hoursStaff hoursUtilisationCost
Packing Stations
Bottleneck
699.5257.822%RM 717
Weighing Scales466.3129.122%RM 192
RF Scanners — Pool A1077.4364.610%RM 139
Pallet Jacks24.716.73%RM 5
Completed deliveries

Sealed, weighed and handed over to shipping — a representative sample of the plan's output.

OrderProfileBoxesCartonsGross weightShip-byStatus
SO-260824-001STD60751.5 kg2026-08-24
Handed Over
SO-260824-002BLK82970.1 kg2026-08-24
Handed Over
SO-260824-003EXP53645.4 kg2026-08-24
Handed Over
SO-260824-004STD76764.3 kg2026-08-24
Handed Over
SO-260825-001BLK79967.7 kg2026-08-25
Handed Over
SO-260825-002EXP51643.8 kg2026-08-25
Handed Over
SO-260825-003STD73761.9 kg2026-08-25
Handed Over
SO-260826-001EXP49642.2 kg2026-08-26
Handed Over
SO-260826-002STD71760.3 kg2026-08-26
Handed Over
SO-260826-003BLK95980.5 kg2026-08-26
Handed Over
SO-260826-004EXP46639.8 kg2026-08-26
Handed Over
SO-260827-001STD68757.9 kg2026-08-27
Handed Over
SO-260827-002BLK92978.1 kg2026-08-27
Handed Over
SO-260827-003EXP59650.2 kg2026-08-27
Handed Over
SO-260828-001BLK89975.7 kg2026-08-28
Handed Over
SO-260828-002EXP57648.6 kg2026-08-28
Handed Over
SO-260828-003STD62753.1 kg2026-08-28
Handed Over
SO-260828-004BLK84971.7 kg2026-08-28
Handed Over
SO-260829-001EXP56647.8 kg2026-08-29
Handed Over
SO-260829-002STD79766.7 kg2026-08-29
Handed Over
SO-260829-003BLK81969.3 kg2026-08-29
Handed Over
SO-260830-001STD77765.1 kg2026-08-30
Handed Over
SO-260830-002BLK78966.9 kg2026-08-30
Handed Over
SO-260830-003EXP50643 kg2026-08-30
Handed Over